PRINCE2 Foundation Guide: Difference between revisions

From EcomEvolve Knowledge Base
Jump to navigation Jump to search
Line 91: Line 91:
A set of 7 broad "best practices" or core values designed to ensure that the project is being managed properly under the PRINCE2 method. '''All 7 principles must be applied if the project''' is truly being managed according to PRINCE2.
A set of 7 broad "best practices" or core values designed to ensure that the project is being managed properly under the PRINCE2 method. '''All 7 principles must be applied if the project''' is truly being managed according to PRINCE2.


=== 1. Continued business justification ===
=== Continued business justification ===


=== 2. Learning from experience ===
=== Learning from experience ===


=== 3. Defined roles and responsibilities ===
=== Defined roles and responsibilities ===


=== 4. Manage by stages ===
=== Manage by stages ===


=== 5. Manage by exception ===
=== Manage by exception ===


=== 6. focus on products ===
=== Focus on products ===


=== 7. Tailor to suit the project environment ===
=== Tailor to suit the project environment ===


== Themes==
== Themes==

Revision as of 16:20, 15 June 2020

Introduction

PRINCE2 stands for PRojets IN Controlled Environments

The "2" denotes the major revision of the method, which was first developed by the Central Computer & Telecommunications Agency (CCTA) in 1989.

Inspired by Prince2 for Beginners : Prince2 Study Guide for certification & project management. By Bryan Mathis.

Benefits

Benefits of using PRINCE2
Benefit Description
Broad applicability Appropriate for any type of project.
Common language Allows practitioners from widely varying environments to use the same vocabulary and methodology.
Product focused Defines the expected outcome of the product and the quality standards used to evaluate it.
Ease of integration Industries that use other project management models will find that PRINCE2 integrates easily with methods specific to one industry.
Clearly defined roles All participants in the project know what is expected of each of them. Continuous monitoring: Project viability is evaluated at every phase of the development process.
Management by exception Provides a framework for escalating problems, known as "exceptions," to the next level of management when they exceed a pre-defined tolerance.
Worldwide adoption and training Numerous resources are available for learning and using PRINCE2 under expert tutelage.

Project definition

PRINCE2 project view
Benefit Description
Change PRINCE2 views projects as a pathway to change. Thus, if a task will introduce noticeable change within an organization, then it's very likely to be a project.
Temporary A project has a clearly defined lifespan, beginning with the decision to move forward with it, and ending when the required product or result is created. Maintenance and minor updates are not part of the project. Major updates are separate projects.
Cross-Functional Because more than one person or department will be affected by a project, it's important to pull together a cross-functional team from many different areas of the company to serve as a task force for the lifespan of the project.
Unique Each project has its own unique set of characteristics that affect how it will be managed. Repetitive tasks that are done the same way repeatedly are not unique and aren't considered projects.
Uncertainty In a project, there are just enough variables that it's impossible to predict everything about the outcome with 100 percent certainty. Uniqueness always produces uncertainty, and uncertainty always produces risk.

The 6 variables / performance targets

The 6 PRINCE2 performance targets
Target Description
Costs Every project has a budget, but that budget can vary, either up or down. The Project Manager must detect cost overruns as early as possible.
Timescales Although ideally, every project should be finished before the deadline, that's not always the case. The sooner the Project Manager identifies a delay, the less inconvenient and costly it will be.
Scope All stakeholders in the project should know what is expected to be delivered in the project, as well as what is not included. The Project Manager's job is to avoid "scope creep," which is the extension of the project's boundaries beyond its defined scope.
Quality PRINCE2 judges quality by the product's suitability for the purpose it serves. Signs of a potential shortfall in quality should be addressed right away by the Project Manager.
Benefits This is the overall purpose of the project and its ability to deliver a return on its investment (ROI). The Project Manager must thoroughly understand this purpose and regularly re-evaluate its potential ROI.
Risk Uncertainty always produces some level of risk, and uncertainty is a characteristic of all projects. The question for the Project Manager is to determine what level of risk is acceptable to the project's stakeholders, and then build in strategies for reducing that risk.

The 4 Elements of PRINCE2

Principles

A set of 7 broad "best practices" or core values designed to ensure that the project is being managed properly under the PRINCE2 method. All 7 principles must be applied if the project is truly being managed according to PRINCE2.

Continued business justification

Learning from experience

Defined roles and responsibilities

Manage by stages

Manage by exception

Focus on products

Tailor to suit the project environment

Themes

A set of 7 specific areas of project management that are continuously and simultaneously monitored and updated throughout the project.

Processses

A series of 7 steps that are carried out in chronological order, starting with the beginning of the project and ending with its closure.

Tailoring

Although PRINCE2 is applicable to any project, it must be tailored to fit a project's type and size.